This is the place to to find updates on Joshua and Crystal's remodeling project. You can add a feed for just this category to your news reader, or simply bookmark this page and check every few days.
To get a little background on what's going on, take a look at our
original letter. As always,
donations are welcome. Thanks for stopping by!
The active todo list! Check back often to track our progress!
- Upstairs wiring Done!
- Basement furring Done! - 2008-09-18
- Media conduit for exterior walls Done! 2008-09-24
- Cleanup for foaming Done! - 2008-09-25
- Have house foamed Done! - 2008-09-26
- Cleanup after foaming Done! - 2008-10-01
- Walls we're replacing/adding
- Bathroom/guest room wall Done! - 2008-10-01
- Laundry room/office wall Done! - 2008-10-06
- Family room/office wall Done! - 2008-10-11
- Furnace room wall
- Kids' room closet Done! - 2008-10-08
- Wiring for light fixtures and switches, including stair light
- Floor reinforcement downstairs Done! - 2008-10-16
- Wiring up interior walls
- Install water heater
- HRV System
- Baseboard plumbing and installation
- Replacing stairs (code compliance)
- Solid foam insulation on downstairs floor
- Resurfacing down stairs floor
- Media conduit for interior walls (including speaker wire conduit and security system conduit)
- Downstairs tub drain replacement
- Plumbing
- Window replacements
- Sheet rock
- Switch/outlet installation
- Underlayment upstairs
- Texture walls
- Priming and painting
- Flooring installation
- Cabinets and vanity installation
- Kitchen appliance installation
- Miscellaneous stuff (light fixtures, etc)
- Move in!
If you go to the rebuild category (http://jjncj.com/blog/categories/1-rebuild) the first post is a "sticky post" giving introductory information. Well, now it's going to serve double duty. I'm going to take my todo list from this post and add it to that